Tender
Announcement
EBS PETROLEUM COMPANY
LIMITED, a company existing under the laws of Hong Kong, with its headquarters
in Hong Kong and the branch office registered in EBS COMPANY Camp, Nahrawan,
Baghdad, Iraq, acting as Operator of EBS Oilfield, is pleased to make the
following public tender announcement:
Tender
Title |
Provision of Drilling
Rig and Integrated Services for Cross Diyala River Area |
Tender Number |
044-SC-25-EBS |
Tender Announcement Website |
1) All
the Bidders should register in our system following the instruction of the
website below (online bidding system): https://erp.ebspetroleum.com/osr/a
2) After
Company Confirmation, only the bidders who have been registered successfully
can download our ITB documents and all clarifications. |
Online Bidding System
Manual |
Bidder
shall follow Section 6 ITB Online Bidding System Manual |
Bid Closing Date |
No
later than 16:00 (Baghdad Time),
on or before 18th
September 2025. In the event that closing date coincides with an
official holiday or curfew, the closing date shall be automatically extended
to the following working day. |
Bid
Delivery |
For
submission online, the bid proposals shall be submitted as per the procedure
specified in Online Bidding System Manual.
For
submission of the hard copy of bid proposal packages, they must be submitted
to the following address: Attention:
Mr. Zhang Xianqiao and Mr. Yang Guang Address:
EBS Petroleum S2 Camp, Nahrawan, Baghdad, Iraq. Tel:
+964 (0) 773 493 7887 and (0) 773 493 7889 |
Tender
Contact Emails |
All clarification and correspondences
from Bidders shall be via the online bidding system. |
Entry
Pass |
Bidder
must provide an entry pass application form (refer to Attachment C in
Section 1) at least 2 working days prior to Bid Closing Date. |
Bid Validity Period |
Subject to Article 12.0 in Section 1, Bidder’s bid Proposal
shall be irrevocable for a period Three Hundred
and Sixty-Five (365) calendar days (“Bid Validity Period”). |
Main Factors |
All
bidders should focus on the below main factors, including but not limited to: (1)
Submission of BID ACKNOWLEDGEMENT (refer to Attachment A in Section 1) (2)
Bid bond submission (3)
Commercial proposal is separate from the technical proposal. (4)
A bidder is considered eligible to participate in tenders if it is not under
suspension or blacklisted in Iraq or Internationally banned. (5)
A bidder and its affiliate are considered unqualified to participate in the
tender if it is part of an ongoing litigation/arbitration with the Company or
the outcome of a litigation/arbitration proved the bidder is in breach,
unless otherwise agreed with related Government authority required by
Company. (6)
Bidders are not allowed to provide goods, works or services under a contract
where they provide consulting services unless otherwise agreed with related
Government authority required by Company. the only exceptions would be
Turnkey Contracts where design, supply and construction activities are an
integral part of the Contract. (7)
A bidder may submit only one bid or participate as a joint venture partner or
Consortium member (if allowed for this tender) in only one bid for each
tender. Failure to comply will result in the disqualification of that bidders. |
Bid Bond |
Bid
Bond: USD 1,000,000.00 (One Million US Dollars), The Bid Bond
must be delivered by hand to the Company in sealed envelope and duly
marked and stamped on outer envelope. Subject to Article 12.0 in Section 1, the original validity of
the Bid Bond shall be the same as aforementioned Bid Validity
Period |
Clarification and
Extension |
Subject
to Article 5/Section 1, Bidders shall submit their clarification request no
later than 7 calendar days before Closing Date, unless otherwise requested by
Company. Subject
to Article 12/Section 1, extension request from bidders shall be made no
later than 3 working days before Closing date,unless otherwise requested by Company. |
Joint Bidding |
Joint/Consortium Bidding is NOT accepted by the COMPANY. |
End